DRAFT COPY - amended June 29, 2007
                             ARS-5 Ashcroft Road Switcher       
        MEMORANDUM OF AGREEMENT BETWEEN CANADIAN PACIFIC RAILWAY CO. & THE TEAMSTERS 
				CANADA RAIL CONFERENCE - Div. 821
Purpose of Agreement 
1.	For the purpose of this agreement Kamloops BC is the home terminal for the 
Ashcroft Road Switcher Assignment. This agreement covers the establishment and 
operation of a road switcher assignment based at Ashcroft BC.
Coverage
2.	Assigned and/or Spare Locomotive Engineers, Conductors and Trainman will be 
governed by the terms of this agreement. 
Specific Language 
3.	It is agreed that effective June 29, 2007 that the ARS-5 Ashcroft Road Switcher 
shall be paid a fixed rate amount of 200 miles per tour of duty at yard rates. 
4.	The crew will consist of a Locomotive Engineer, Conductor, and Trainperson. 
5.	The ARS-5 Assignment will operate as follows. The crew will be transported 
from Kamloops to Ashcroft. At Ashcroft the crew will perform the required switching 
until their work is completed. The crew will then be transported back to Kamloops. 
6.	The ARS-5 Assignment will operate Monday-Friday from 0600-1800.  Saturday and 
Sunday are the assigned rest days.
7.	The entire crew on this assignment must be available if required for up to 
twelve hour per tour of duty to qualify for the fixed rate. The twelve hours 
includes the transportation time to and from Ashcroft.
8.	If any member of the crew serves notice for rest in accordance with Article 27.04 
(TCRC-Engr), or Article 29 (TCRC-Cndr), the crew will no longer be considered to 
be on the fixed rate and will be compensated as per the respective Collective Agreement. 
9.	If rest has been booked and CMC decide to send relief for a specific crew 
member(s) the remainder of the crew will still be entitled to the fixed rate of pay. 
10.	In the event employees are on duty in excess of 12 hours they will be compensated 
on a per minute basis at a rate of double the hourly pay (Yard Rates) for all time 
so occupied in addition to the established fixed rate.
11.	If ARS-5 is cancelled on any working day (except on a GH) before reporting for 
duty, the crew will be entitled to payment of 100 miles at Yard Rates for each day 
they are cancelled. 
12.	There are no additional premiums for working on a General Holiday. Employees 
will be paid an amount equal to the earnings for the tour of duty prior to the 
General Holiday.
13.	The 30-mile road switcher limit set forth in the collective agreement is not 
to be exceeded by the ARS-5 except as provided for below. 
14.	In instances where the company requests the crew to exceed the 30 mile limit, 
the TCRC agree they may be used up to a maximum of 50 track miles from the 
OMTS's @ Ashcroft.
15.	If the company uses the ARS-5 crew in the extended road switcher limits of 
between 30 and 50 miles, an additional payment of 100 chargeable miles (@ Yard 
Rates plus all arbitrary payments (that apply while exceeding the 30 mile limit 
ie. C-only, KDA, etc.) will be paid to the crew in addition to the established 
fixed rate. 
Transportation
16.	The company agrees to provide or arrange for suitable transportation services 
from Kamloops to Ashcroft and return on a daily basis. Transportation will be made 
available in Kamloops at the Yard Office at 0600 daily on scheduled work days.  
17.	If the crew member(s) and the company mutually agree, the crew member(s) may 
elect to use a personal automobile and receive the automobile mileage allowance 
specified in the Collective Agreement. Each member of the crew will be entitled 
to make claim for this payment.
Cancellation Clause 
18.	This agreement is without precedent or prejudice to either party and can be 
amended, revised and/or cancelled with thirty days written notice by either party 
signatory to this agreement.
Signed this ___ day of June 2007


___________________________________
Mr. T. Litowski
CPR Manager Operations


___________________________________
Mr. F. O'Genski
TCRC - LC Conductors


____________________________________
Mr. E. DiCredico
TCRC - LC Engineers